An exceptional working day allows you to make a normally non-working day a working day.
This feature can for example be used to make up for a delay by working on a Saturday or Sunday.
Add an exceptional working day
- Open your Project.
- Click on Planning.
- Open the Disruptions & Exceptions tab.
- Click on +.
- Select Add an exceptional working day.
- Enter the title.
- Add the affected Tasks.
- Select the day to make a working day.
- Enable Automatically adjust the End date of Tasks if you want to recalculate dates.
Select the affected Tasks
In Affected Tasks, add the Tasks that will be worked on during this exceptional day.
Once the Tasks are selected, Archipad suggests the Non-working days corresponding to their period.
Choose the day to make a working day
In Days to make working days, Select the desired day or days.
Note: no day is suggested until a Task has been selected.
First Select the affected Tasks.
Check the impact
The Impacts section allows you to view:
- the initial End date;
- the new End date;
- the adjustment applied.
An exceptional working day can bring forward the End date of a Task.
However, subsequent Tasks are not automatically brought forward. Modify their dates manually if necessary.