I moved a Task forward, but the next Task was not moved forward.

Smaheine
1 min read

In this article

Why the next Task did not move forward

This is the expected behavior.

Dependencies allow Tasks to be automatically postponed in case of a Late, but they do not move them forward when a Task finishes earlier.

Manually modify the Start date of the Task in “Working days to return”.

First add at least one Task in Affected Tasks.

Archipad will then suggest the Non-working days included in the period of these Tasks.