The Gantt view lets you visualize Planning tasks on a timeline.

It helps you quickly understand how tasks connect, their duration, and the Dependencies between different project stages.

Access the Gantt chart

  1. Open your Project.
  2. Click on Planning in the sidebar menu.
  3. Open the Gantt tab.

Tasks created in the Task tab appear automatically in this view.

Read the Gantt chart

In the Gantt chart, you can visualize:

  • Tasks as bars;
  • Milestones;
  • Task duration;
  • Dependencies between tasks;
  • How different project Phases connect.

Element positioning helps you quickly spot overlaps, work periods, and potential delays.

View the impact of a change

Changes made in Planning are reflected in the Gantt chart.

You can use it to verify:

  • task delays;
  • the impact of a Disruption;
  • Milestone shifts;
  • how Dependencies affect downstream tasks.